Middlesex County Council Meeting
Re: Nextera: Transmission/Road Allowance
Date: November 27
Time: 1:00 pm
Place: Middlesex County Building, 399 Ridout St. North, London MAP
Nextera Letter to Middlesex County Council
In Middlesex County, Nextera has two wind projects up for final public comment: Adelaide and Bornish, totaling 83 turbines, for now. The company’s plan is to connect these two projects, as well as the 92 turbine Nextera Jericho and 62 Suncor Cedar Point projects, with one massive transmission line. Problem is, the route isn’t figured out yet. Remember, the public is supposed to be filing their final comments right now on complete project documents, and yet this very significant piece of information isn’t available for the public to comment on, or even view.